|
Online edition of India's National Newspaper Wednesday, July 04, 2001 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
City deprived of new train services for want of overpass
By Our Staff Reporter
BANGALORE, JULY 3. Mr. B.Krishnakumar, Divisional Railway
Manager, Southern Railway, Bangalore, said today that the
Railways could not start new train services to Bangalore from
other States because of the delay on the part of the State
Government in sharing the cost of an overpass to be built near
Lingarajapuram in the City.
Speaking to presspersons after flagging off the Yeshwanthpur-
Vasco Biweekly Express here, Mr. Krishnakumar expressed concern
over the delay in the construction of the overpass.
He said a railway line between Yeshwanthpur and Byappanahalli had
already been laid at a cost of Rs. 20 crores. But trains could
not be run on the track because of protests by people in support
of an overpass near Lingarajapuram.
New trains on the Salem-Yeshwanthpur-Hubli line could not be
started because of the delay in the construction of the overpass.
It had also affected the Yeshwanthpur-Salem line. The Pune-
Ernakulam Express, which was supposed to run via Yeshwanthpur,
would now run on the Konkan railway line, he added.
However, the Bangalore Mahanagara Palike (BMP) had agreed to
provide 50 per cent of the cost of the overpass, and tenders had
been invited for work on it. People of Lingarajapurm had agreed
to allow night trains once the railways started work on the
overpass, he said.
Railway terminal
He said the railway terminal at Yeshwanthpur would become fully
operational by January 1, 2002. The Yeshwanthpur-Vasco Express
would start operating from the new terminal shortly.
The Railways had earmarked Rs. 17 crores for the terminal, and
Rs. 3.5 crores had already been released. Facilities such as
station building, pedestrian overpass and one pit line would be
provided. The pit line would be ready by December and the
Yeshwanthpur-Howrah Express would be flagged off on January 1, he
said.
As per the plan, two pit lines would be constructed at the
terminal. Each line would maintain three long route trains. Once
the lines were ready, six trains could be operated from
Yeshwanthpur. The plan envisaged construction of two more pit
lines. However, introduction of new trains depended on the
construction of the overpass, he added.
Mr. Krishnakumar said the entrance to the new terminal would be
from the NH 4. A proposal had been submitted to the State
Government urging it to allow the land in front of the terminal
for a bus-bay to be used by the BMTC.
Proposals had also been submitted to the Southern Railway
Headquarters to allow trains such as Rani Chennamma Express,
Bangalore-Hubli Inter-City Express and Swarna Jaynthi Express to
stop at Yeshwanthpur, he added.
He said the terminal at Yeshwanthpur had to be developed into a
full-fledged railway station as the Bangalore City Railway
Station could not be expanded further.
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : Will the Bangalore international airport project take off? Next : Work on five mega city projects to start soon | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2001 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|