|
Online edition of India's National Newspaper Sunday, May 21, 2000 |
|
Front Page |
National |
International |
Southern States |
Opinion |
Business |
Sport |
Science & Tech |
Miscellaneous |
Features |
Other States |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
Stage I of UKP yet to be completed
By Our Special Correspondent
HUBLI, MAY 20. Karnataka has begun preparations for fixing skin
plates on the crest gates of the Alamatti Dam of the Upper
Krishna Project, with a view to impounding water up to a height
of 519.6 metres when monsoon begins.
The State is still awaiting sanction from the Union Government
for the Stage II of the UKP. However, it has not completed work
sanctioned as part of Phase II of Stage I of the project. The
work has been going on since 1989, and unless it is completed,
Karnataka will not be able to make much progress in its efforts
to utilise water impounded in the Alamatti Dam.
Phase II of Stage I of the UKP envisages raising the height of
the Alamatti Dam up to 509 meters, construction of 18
distributaries under the Shahpur Branch Canal, completion of 50.8
km of the Mudbal Branch Canal along with distributaries and 64 km
of Indi Branch Canal with distributaries, construction of 672 km
of roads, establishment and maintenance of a Water and Land
Management Institute (WALMI) for imparting training, and
rehabilitation and resettlement (R&R) programmes for the people
affected by the project.
The work, which was estimated to cost Rs. 791.67 crores, was
undertaken in 1989 with Rs. 308 crores from the World Bank. The
main objective of Phase II was to irrigate 1.5 lakh hectares, to
provide employment to one lakh families.
Work, which was to have been completed by December 1996, had not
been done even by March 1999. Work on canals and distributaries
is yet to be completed.
The delay has affected creation of irrigation potential. Although
a capacity to irrigate 1.18 lakh hectares was created, the actual
area irrigated was only 48,583 hectares. The expenditure was 135
per cent of the estimate.
The price paid for the delay is quite staggering. The original
estimate of Rs. 791.67 crores in 1989 was revised to Rs. 1726.30
crores in 1995, and to Rs. 2,417 crores in 1997. A total of Rs.
1,017 crores had been spent by the end of June 1997. As a result
of the delay, the cost of various components of the project
increased from 50 to 740 per cent by July 1995. The cost of
irrigation per hectare went up from Rs. 53,000 to Rs. 1.61 lakhs.
The poor implementation of the R&R programme led to the World
Bank stopping aid in June 1997 -- Rs. 111.86 crores was due from
the bank at that time.
An audit in March 1999 attributed the increase in the project
costs to higher cost of land acquisition (Rs. 5 crores), high
tendered rates (Rs. 84 crores), change in parameters and scope of
the Alamatti Dam (Rs. 22 crores), additional submergence and
changes in the R&R package (Rs. 461 crores), and payment at
increased rates (Rs. 291 crores).
While the agreement with the World Bank stipulated that the State
Government ensure adequate budgetary provision and timely release
of funds, no separate funds were earmarked for Phase II. Funds
were included in the total yearly provision made for the UKP.
As per the Staff Appraisal Report (SAR) and the Revised
Implementation Schedule (RIS) from 1988-89 to June 1997,
construction under Phase II was sluggish throughout the period of
execution of the project. The shortfall in achievement of the
target was between 38 per cent and 53 per cent between 1989 and
1993. Even after targets were revised as per the RIS, the
shortfall in achievement of the target was between 30 per cent
and 70 per cent during 1995-1997.
It has also been revealed in the audit that there was delay in
acquisition of land, supply of water to contractors for
construction of Indi and Mudbal branch canals and settlement of
disputes relating to the claims of the contractors and disputes
over use of mechanical lining equipment in respect of Indi and
Mudbal branch canals. Adequate funds were not released in the
early years of the project. These indicate the Government's
failure to synchronise work on the project, says a report of the
Comptroller and Auditor General of India.
The State Government has failed to take note of serious
deficiencies noticed in the Narayanpur Left Bank Canal (NLBC)
since October 1994. The failure to irrigate the extend of land
envisaged under Phase II is due to the defects in the NLBC.
The NLBC was completed in Phase I of Stage I of the UKP for a
total discharge of 10,000 cusecs of water. The discharge required
to meet the irrigation potential under Phase I and Phase II was
1,900 and 2,800 cusecs, respectively. In 1997, the Indian
Institute of Science, Bangalore, made a study on the stability of
the NLBC at the request of the Government, and in 1998, the
hydraulics of the canal was tested by the Karnataka Engineering
Research Station (KERS).
The study by the IISc. reportedly revealed that the canal was
weak in the stretch from 46 km to 70 km, and that it was not
capable of carrying a discharge beyond 2,300 cusecs (23 per cent
of capacity). The final report is awaited. The KERS reported that
the project authorities were oblivious of the existence of the
calibration cures prepared for the Head Regulator. As the total
discharge required for Phase I and Phase II is 4,725 cusecs, the
failure of the NLBC poses a serious threat to the efficiency of
the project, it is said.
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : Hampi may remain as a World Heritage Site Next : A touching invitation to a coveted honour | |
|
Front Page |
National |
International |
Southern States |
Opinion |
Business |
Sport |
Science & Tech |
Miscellaneous |
Features |
Other States |
Classifieds |
Employment |
Index |
Home | |
|
Copyright © 2000 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|