|
Online edition of India's National Newspaper Monday, October 16, 2000 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home |
|
Opinion
| Previous
| Next
Recharging the power sector
By V. Jayanth
AT A time when the Centre was giving a determined push to the
power sector and coaxing State Governments to undertake major
reforms of their electricity boards, a change of guard came about
in the Union Power Ministry. With the untimely passing of
Rangarajan Kumaramangalam, Mr. Suresh Prabhu has taken over the
reins. It will take some time for him to come to grips with the
crisis and push ahead with critical reforms.
The problems are both political and financial. Unless politicians
gather the courage to take hard decisions now, the efforts to
substantially enhance power generation at least in the Tenth Plan
period could be undermined. To accelerate growth and correct
regional imbalances in development, power is one of the prime
requisites. The Eighth Plan envisaged a capacity addition of
40,000 MW but ended up providing hardly 24,000 MW. After a mid-
term review of the Ninth Plan, the Government again scaled down
its target. Against an original projection of 40,245.2 MW, it is
now considered feasible to add only 28,097.2 MW by 2002.
At present, the installed capacity in the country is just over
95,500 MW (72 per cent thermal, 24 per cent hydel and the
remaining nuclear and wind energy). Perspective plans by the
Central Electricity Authority estimate a requirement of about
2,40,000 MW of installed capacity by 2011-12 for self-
sufficiency. Even now, there is a shortage of between 5 and 8 per
cent in supply. Though the process of reforms was set in motion
in 1992 and the Centre volunteered to provide counter-guarantees
for some mega power projects cleared in the initial rush of
investments, only a few have gone on stream. A majority of the
private projects remain in the pipeline, held up by bottlenecks -
financial or environmental.
Kumaramangalam took a series of initiatives to push reforms and
get the States to take the lead in increasing power generation.
The Electricity Regulatory Commissions Act, 1998, was the first
concrete step to reform the sector and provide an escape route
for politicians ruling the States from the `tariff trap'. Apart
from setting up a Central Electricity Regulatory Commission
(CERC), the Act enabled the States to set up their own
Commissions - SERCs - for depoliticising pricing of power. The
SERCs are supposed to rationalise tariff, introduce transparency
about subsidies and promote efficient and environmentally benign
energy policies. The CERC was set up in 1998 and since then at
least 14 States have gone through the formalities of establishing
the SERCs, but some of them (Tamil Nadu, for instance) are still
not functional.
After several formal and informal consultations, the Centre
called a Power Ministers conference in February this year,
getting the Prime Minister, Mr. A. B. Vajpayee, to inaugurate it
and impress on the States the urgency of reforms and the need for
putting the State Electricity Boards (SEBs) in order. Though a
complete consensus on thoroughgoing reforms was elusive, a broad
agreement was reached. Basically, the Ministers agreed on an
energy audit at all levels, a time-bound programme to install
meters for all consumers by December 2001, reduction and ultimate
elimination of power theft, and strengthening/upgradaing of sub-
transmission and distribution systems by taking the sub-station
as a unit on a priority basis.
The Centre recommended the `unbundling' and corporatisation of
the SEBs, benchmarking through separate distribution profit
centres and promotion of competition in the power industry. The
preferred model was the trifurcation of the SEBs into generation,
transmission and distribution corporations. An attempt to
introduce a common, Central legislation - the Electricity Act
2000 - is still being resisted by some political parties and many
State Governments. But the Centre is trying to initiate a debate
and build a consensus on it.
While working on the Ninth Plan, the Centre approved an outlay of
Rs. 1,24,526.41 crores, of which Rs. 53,299.41 crores would come
under the Central sector itself. The States were supposed to pool
in Rs. 71,227 crores. But a major portion - 43 per cent - of the
targeted capacity was to come up in the private sector, while
multilateral agencies such as the Asian Development Bank and the
World Bank were also approached for financing.
But the basic precondition for private, foreign or multilateral
investment was reform of the power sector. Any investor wanted
`fair pricing' of electricity and the Centre even offered a 16
per cent return on investment, when the SEBs could not earn any
profit after decades. Since the SEBs were the only agencies
involved in transmission and distribution, they had to guarantee
the purchase of all power generated. A Power Purchase Agreement
(PPA) was to be signed and escrow provided, and finances were to
be tied up for `financial closure' of the proposed private
projects. Unfortunately, many producers have not been able to
achieve even the financial closure stage. Of the 57 private
projects cleared till June 2000, only nine have been fully
commissioned and 11 are under construction.
Ultimately, the problem boils down to the financial viability and
sustainability of the SEBs. Together, the SEBs owed the National
Thermal Power Corporation (NTPC) - one of the leading producers
of power - Rs. 14,744 crores including a surcharge of Rs. 5,371
crores - as of June 2000. Bihar tops the list with an outstanding
of Rs. 2,663 crores, followed by Delhi and Uttar Pradesh with
over Rs. 2,500 crores. Though the NTPC threatened to shut off
supplies to the defaulting States and resorted to token cuts,
nothing much was achieved because of the politics involved. So
the Centre cleared a special scheme to recover these dues. This
debt would be `securitised' - converted into tax-free bonds,
which would be issued either to the undertakings or other bidders
which have the counter-guarantee of the State Governments.
If the SEBs are not in a position to pay even the Central sector
undertakings such as the NTPC, which supply power at reasonable
rates (Rs. 2 plus a unit), how can they ever afford to pay the
private producers who will charge anything upwards of Rs. 3.40?
Most, if not all, of the SEBs are running at a loss and depend on
the State Governments to reimburse the subsidies - of free power
to farmers, highly subsidised energy to the poor and partly
subsidised electricity to domestic consumers. The Centre wants
the States to trifurcate the SEBs, budget the subsidy and
introduce competition in the transmission and distribution
sectors as well. Above all, the key to financial viability lies
in cutting down drastically on transmission and distribution
(T&D) losses so that the SEBs can earn more from the generated
power.
Apart from Mizoram and Jammu and Kashmir , which have a T&D loss
of 47 per cent, Delhi reported a loss of 46.86 per cent (1997-
98), Andhra Pradesh 31.76 per cent and Assam and Arunachal
Pradesh over 30 per cent. About half a dozen other States lost
between 20 and 25 per cent. Hence the importance of containing T
and D losses, the bulk of which is caused by vested interests in
the industrial and commercial consumers category who allegedly
steal power, with the connivance of some officials.
So, the responsibility finally devolves on the States to accept
power sector reforms. If they continue with the short-sighted
policy of populist schemes with an eye on elections, they could
be left behind in growth and development. Even Andhra Pradesh,
which corporatised its SEB, is stiff facing problems because of a
political agitation against tariff revision. As different parties
rule the various States, it will be better to depoliticise the
power sector and let the SERC handle the ticklish tariff issue.
Send this article to Friends by E-Mail
|
|
Section : Opinion Previous : The Vajpayee caravan rolls on Next : Astounding observation | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2000 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|