|
Online edition of India's National Newspaper Tuesday, December 05, 2000 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
Completion of bus terminus likely to be delayed
By Our Staff Reporter
CHENNAI, DEC. 4. Pressure is mounting over the completion of the
Chennai Mofussil Bus Terminus (CMBT) project which seems to be
heading towards inevitable delay. The attempts to inaugurate the
project before the elections could be dampened with contractors
being posed with an advanced deadline.
The recent rains has added to the woes of the contractors
undertaking the project, when an independent slab sheltering a
walk-way inside the ongoing bus terminus project collapsed on
Thursday evening.
Though the incident, in which no casualty was reported, sent
shockwaves among the contractors and officials, the Minister in-
Charge of the CMDA, Mr. K. Ponmudi, is said to have ordered a
report on it at record speed.
Sources said after the Minister was informed about the collapse
on December 1, an order was issued directing the CMDA to deploy
an engineering committee to study the cause and submit a report
by December 7.
While the committee constituted by the CMDA, comprising experts
from the department of Highways Research Studies (HRS), IIT and
Anna University, are conducting the study, the work to cast rings
and construction of the main dome will be halted.
It is expected that more time will be taken to carry out a
detailed study to ensure that the problem will not persist during
or after the construction of the main dome or the bus bays.
Severe damage and threat to lives is inevitable if the huge
structure is constructed without a detailed review at this stage,
officials felt.
The 34 acres of land that had been earmarked for the bus terminus
was initially a sewage farm. It had been studied for feasibility
initially by experts from the Anna University.
The CMDA had sought land further away from the sewage farm in
Koyambedu. However, the land required by the agency was
sanctioned for the construction of the SAF games village.
The feasibility study of the sewage farm which was finally
allocated for the CMBT was `comprehensive and convincing', CMDA
officials said. There was no possibility of the structure sinking
in as a hard friction piling foundation had been laid before
raising the structures, they said.
Preliminary reviews to the damage hinted at the complex design
involved which could have collapsed in the wind, they said.
Meanwhile, it had become apparent that the project was unlikely
to be completed by mid February as announced by the Minister
recently.
The contract period for the project expired only by May, 2001,
but the contractors were now being asked to complete it by
February.
With more funds sought by the contractors to employ additional
manpower also being rejected, the contractors have made it clear
that completion of the project with a shorter deadline was not
possible.
It is now hoped that at least the passengers resting hall and the
bus bays would be completed by the expected date, which could
enable `at least partial functioning' of the terminus sources
added.
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : Mullaperiyar row takes a political turn Next : Babri Masjid Demolition Day: Security beefed up | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2000 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|