|
Online edition of India's National Newspaper Thursday, August 16, 2001 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Science & Tech |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
Cost increases four-fold due to inordinate delay
By K.N.Reddy
BIDAR, AUG. 15. While it is noteworthy that the Public Works
Department (PWD), on the one hand, is trying to complete at a
feverish pace the construction of 100 new bridges in the State to
ensure better road linkages, it is, on the other hand, turning a
Nelson's eye to the completing the construction of bridges which
have been partly built over several years.
Two such bridges which need immediate attention are the Kandagul
and Chillargi bridges across the Manjra in Bidar District.
The work on these bridges -- one connecting Bidar taluk with
Aurad taluk (Kandagul), and the other connecting Bidar District
with Narayankhed, Nizamabad, and other places in Andhra Pradesh
-- has stopped for the last four years.
These two inter-State bridges, which are vital for commuting
between Karnataka and Andhra Pradesh are an example of how such
delay in execution of projects can affect costs besides causing
hardship to the public.
The bridges also serve as an example of how lack of co-ordination
between Karnataka and Andhra Pradesh can affect the completion of
inter-State projects. Thanks to the delay, the revised estimates
for these bridges is said to be Rs. 20 crores as against Rs. 5.3
crores in 1988.
The Kandagul and Chillargi bridges were conceived in the early
1980s following construction of a reservoir
across the Manjra near Singur village in Medak District in Andhra
Pradesh. The reservoir was planned to augment the supply of water
to the twin cities of Hyderabad and Secunderabad.
The backwaters of the Singur Project extends up to Janawada
village in Bidar taluk. As the depth of water in the river at
Chillargi and Kandagul villages is 8.70 m and 5.90 m.
respectively when the reservoir is full, several border villages
in Karnataka and Andhra Pradesh are cut off. Therefore, to
compensate for the inconvenience caused to the people following
the construction of the Singur Reservoir, the Andhra Pradesh
Government agreed to bear the cost of constructing the two
bridges.
An order to this effect was issued in 1984. However, it took four
years for the two governments to prepare plans, estimates (Rs.
2.5 crores for Chillargi and Rs. 2.8 crores for Kandagul at 1988
rates), and to complete other formalities. Administrative
approval was given to the projects in September 1988.
Thereafter, it took three years to finalise the contractor and
hand over the construction to a Hyderabad-based company on a
"lumpsum" basis. The "lumpsum" amount quoted by the contractor
for the Chillargi and the Kandagul bridges was Rs. 360.50 lakhs
and Rs. 403.50 lakhs respectively, and the deadline set was 1995.
But there was an inordinate delay in releasing the funds in 1992
and 1994 by the Andhra Pradesh Government which affected the
execution of works. The Andhra Pradesh Government has so far
deposited an amount of Rs. 10.45 crores for the two bridges.
In the case of the Chillargi bridge, the foundation and
substructure work of all piers and abutments have been completed.
The bridge is proposed to have 25 spans of 23 m. length each
centre to centre. While the approaches on both sides of the
bridge have been completed, the super structure works are yet to
be completed. The expenditure incurred so far on this bridge,
including the cost of land acquisition, is Rs 457.45 lakhs.
In the case of the Kandagul bridge, the foundation and sub-
structure work of all piers and abutments have been completed.
Sixtynine pre-stressed concrete beams have been cast and set in
the required position. But the RCC deck slab work is yet to
commence. The expenditure incurred so far on this work, including
the approaches, land acquisition, etc. is Rs. 555.67 lakhs.
Sources in the PWD here told THE HINDU that the contractor
abandoned the work in 1997 demanding revision of costs at current
rates.The revised cost as per current schedule of rates works out
to Rs.20 crores. The contractor's claims were submitted to the
Chief Engineer, C&B (North), Dharwad, in January 2001, for
approval.
Since water has been impounded in the reservoir, the link between
the villages on either sides of the river has been cut off.
People have to use boats to cross the river.The immediate task
before the State Government is to take up the matter with the
Andhra Pradesh Government and persuade it to release the funds to
complete the construction of the bridges at the earliest. Further
delay will render whatever works completed so far waste.
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : Govt. to mobilise Rs.10,900 cr. this year Next : A link with Bangalore's hoary past revived | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Science & Tech |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2001 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|