|
Online edition of India's National Newspaper Tuesday, August 21, 2001 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
GAIL pipeline commissioned
By Our Staff Reporter
VIJAYAWADA, AUG. 20. The Gas Authority of India (GAIL) will
complete the 600-km Visakhapatnam-Secunderabad gas pipeline in 24
months, Mr J.K. Jain, Chairman and Managing Director, said here
today. Mr Jain commissioned the 205-km gas pipeline laid from
Tatipaka, East Godavari district, to Lanco-Kondapalli power plant
near here today. He also inaugurated the GAIL gas terminal in the
Kondapalli Industrial Development Agency.
He said construction of the Visakhapatnam-Secunderabad pipeline
had already began. GAIL had set for itself a target to supply gas
to the BSES power plant from October 15. About the availability
of gas Mr. Jain said GAIL had access to about 5.8 to 5.9 million
cubic metres a day. An effort was on to increase it to nine
million cubic metres a day.
Mr Jain said the Lanco-Kondapalli pipeline was completed 10
months ahead of schedule with the help of the State Government.
He said even farmers were also very cooperative. He said for the
first time even the customer, Lanco-Kondapalli power plant, was
very helpful. He said the power plant had already made the
changes needed for generating power with gas. He lauded the
standards being maintained in the power plant.
GAIL laid the pipeline to Kondapalli Industrial Estate at a cost
of Rs 300 crores. The laying of the pipeline was done in four
packages of 19.5 km(Chinchinada bridge), 45 km, 60 km and 80 km.
The pipeline was laid across the Vasista Godavari, a major river,
two minor rivers, 17 major canals, 93 minor canals, 100 roads and
through the limits of 89 villages.
The pipeline project was conceived in February 2000, and the
detailed survey was completed in July 2000. The gas supply
contract was signed with Lanco-Kondapalli exactly a year ago on
August 21, 2000. Construction began on March 11, it was tested
first with water initially on July 22 and finally on August 15.
It was `purged' with nitrogen on Sunday and commissioned today.
The cost of transporting gas through the pipeline was Rs. 4.88
crores per month.
Mr. Y. Harish Chandra Prasad, Managing Director, Lanco-Kondapalli
Power Project, said GAIL allotted 1.12 million cubic metres of
gas per day. The capacity of the pipeline was much more than what
was required by Lanco. The additional gas could be used by other
industries in the industrial estate, he said.
He said generating power with gas would cut production cost by 50
per cent. Lanco was at present generating power with naphtha
producing one unit for Rs 4.60. The power plant would be able to
reduce the cost of production to Rs 2.30 a unit. This would save
the State Government between Rs 150 crores and Rs 200 crores a
year. Lanco which had an installed capacity of 355 MW was
producing 7.5 million units a day, he said.
Mr Chukkapalli Suresh, Director, Lanco, said that the Chief
Minister, Mr N Chandrababu Naidu, was closely monitoring the
progress of the pipeline. The GAIL General Manager, Mr D.K.
Purwar, the Executive Director, Mr B.S. Negi, the Director, Mr
S.P. Rao and the Lanco General Manager, Mr S. Seetaramiah, spoke.
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : New organisation formed for cause of Babri Masjid Next : Cable operators face threat of boycott | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2001 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|