|
Online edition of India's National Newspaper Thursday, September 13, 2001 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Science & Tech |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
HB failed in demand assessment, chose wrong sites: CAG
By R.K. Radhakrishnan
CHENNAI, SEPT. 12. Over 50 per cent of the units constructed by
the Tamil Nadu Housing Board under the `small and medium towns
scheme' could not be sold as it failed to assess the demand and
because of wrong site selection.
As many as 1,206 out of the 2,120 houses had no takers, resulting
in blocking of Rs. 17.01 crores of board funds.
According to the latest Comptroller and Auditor- General report,
the board completed construction of the houses at a cost of Rs.
27.65 crores under nine schemes by March 1997.
But till December 1999, 1,206 houses remained unallotted. At
Udumalpet, where houses worth nearly Rs. 5 crores remained
unallotted, the site was six km away from the town and there were
no frequent bus facilities. Besides, the location was surrounded
by agricultural land and the cost worked out by the board was
much higher than the market value.
At Srivilliputhur, 217 houses worth Rs. 2.93 crores remained
unallotted. High cost, roof leakage, non-availability of
borewells for drinking water were among the reasons cited for the
poor patronage for the project.
At Chengam, 86 of the 100 houses had no takers. The project was
located in a backward area and local residents threatened buyers
from outside.
There was another factor too which led to the poor buyer-
interest. Deposits were not taken from ``provisional allottees.''
This despite the Board deciding in 1991 that as soon as tenders
were finalised, lots be drawn, provisional allotment be made and
an initial deposit of 30 to 40 per cent be collected from the
allottees. The CAG notes that though all nine schemes were
sanctioned after this decision, the executive engineers of the
executing divisions failed to follow this procedure.
The board lost in selling shops in its commercial complexes too.
For, the sale price was fixed at rates much higher than the
market rate, notes the report. As many as 39 shops were left
unallotted, resulting in non-realisation of a revenue of about
Rs. 7 crores.
In its reply to the CAG, the Government, in October 2000, said
land acquisition was time-consuming and that there was a two to
three-year gap between demand assessment and actual completion
which led to poor demand. But the board was able to sell all
houses under 77 other schemes; only these nine the CAG looked
into had problems.
``The reply was not tenable since the cost of the houses
escalated, on an average, from 203 to 247 per cent of the
advertised cost even at the time of administrative sanction and
there was a clear failure on the part of the board in not
reassessing the demand before the commencement of commercial
construction. As regards the claim of good sale of houses under
other schemes, it was noticed that in 16 more schemes 825 houses,
valued at Rs. 24.89 crores, remained unallotted till September
2000.''
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : Plus-Two 'improvement' students in a quandary Next : Burglar alarm installed in Tirumailai station complex | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Science & Tech |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home | |
|
Copyright © 2001 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|